SUMMER PROJECT UPDATE – SEP. 25, 2019

SUMMER PROJECT UPDATE – SEP. 25, 2019

  With many of the larger jobs associated with our summer snowmaking project already completed, the focus now has primarily turned to completing the construction of our pump house; the heart of our system you could say.   PUMP IN PLACE – With the...
SUMMER PROJECT UPDATE – AUG. 6, 2019

SUMMER PROJECT UPDATE – AUG. 6, 2019

  Progress, while it may feel like it’s slowing down due to the completion of trenching / ditching for waterline, is still full steam ahead.   TRENCHING COMPLETE – Some of the more intensive and intrusive work is now complete; that is trenching /...
SUMMER PROJECT UPDATE – JULY 22, 2019

SUMMER PROJECT UPDATE – JULY 22, 2019

  Over the past couple of weeks, crews have made their way into the base area, in the vicinity of the base of the Huckleberry Chairlift. Work within this area is substantially more complicated than it is up on the mountains due to the presence of existing...
SUMMER PROJECTS UPDATE – JUNE 25, 2019

SUMMER PROJECTS UPDATE – JUNE 25, 2019

Construction crews are working on all fronts at Castle Mountain Resort this week, now that our propane gas system has been switched off and ATCO is on-site daily.   Lone Ranger Trenching Completed – Over the weekend, pipe and electrical work on Lone Ranger...
SUMMER PROJECTS UPDATE – JUNE 17, 2019

SUMMER PROJECTS UPDATE – JUNE 17, 2019

Welding Nears Completion – Progress on our summer projects continues to move along, especially on the snowmaking side of things. Over this past week our primary contractor completed welding together long sections of pipe, many of which have already been moved...